We are near completion of our project at 482 Broome Street in New York City. When we initially started the project, the facades were very deteriorated and had some graffiti writing on the west facade. The project began in mid-October with the installation of the sidewalk bridge and scaffolding. Following that, we cleaned all the facades and began pointing and masonry repairs. After getting most of the pointing completed, we worked on some window repairs and painting. We are currently finishing up some paint removal and minor repairs before the scaffolding is removed and the project is fully completed.